Bolton Essa Academy: Case Study

10th February

Project: Linear DC–Bolton Essa Academy

Project Budget: £7,500.

Project Timescale: 3 weeks

Project Location:  Lever Edge Ln, Bolton BL3 3HH

Project Objectives: To supply and install new floor coverings to classrooms, including all vinyl-capped and coved up the walls at 100mm

Work Completed: 

Forbo Marmoleum Real; Spa 3219/321935 was installed to all science rooms.

Forbo Safestep R11 Lava 174592 was installed all Food & Catering Classrooms.

Project Outcome: As this was a live school, we had to follow strict guidelines and ensure enhanced DBS checks were in place to be allowed access on site. We also worked out of hours some nights to enable our preparation works were carried out efficiently, and so no other trades were held up from our work.

“The Team at Mayfield Floors did a fantastic job at the recently completed Essa Academy project. The product specified and installed was to a very high standard. The project had a number of logistical issues and the team worked really well to accommodate those issues, and streamline the installation. Looking forward to working with the team again in the future.“ – Matt Hurley, Senior Project Manager

 