Recently, we finished a huge job at Talmud Torah Chinuch Norim School where we installed ceramic floors and wall tiles around the majority of the building. Take a look at the project details below:

Project Name: PLP Construction / TTCN Primary School

Project Budget: 48k

Project Timescales: 8 Weeks

Project Location: Cheetham Hill

Project Objectives:  Installation of ceramic floor and wall tiles to classrooms, corridors, communal areas, staircases, toilets, staffrooms. New build. Fit only.

Work Completed: 48,437 sqft of tiles. Ceramic tiles (Specifics).

Project Outcome: Our staff worked in shifts in order to maintain the programme while so other trades could carry out their work.

If you’re looking for a commercial flooring company that works to the highest standards and goes the extra mile to meet the specifics of your project. call us on 0161 477 5580 or get in touch via our website.